The HOUSE Project: The longest month…

July 1, 2014

It’s only been about a month since we settled on our town house and it officially became our “old house” (Caelan calls it the “empty house” or the “dirty house”, not sure why). We’ve been settling into our apartment and things are going well. The kids are sharing a room and there is plenty of space for both of them. We did run into a pretty significant sleep regression with Leah and as much as we didn’t want to have to do this in the apartment, we had to do a sleep training refresher. Thankfully, she’s back on track…sort of…some days. Sorry neighbors :/

In the past month, we’ve been unusually busy with moving and unpacking, birthday parties, new babies, and family time. Usually when you’re really busy, time flies by and we’d sure love that since all we’re doing right now is waiting for our house to be built. But somehow, the past few weeks have draaaaaaaaaaaaaagggged on forever! It’s only been a month?! Really?! And we still have 2-3 more months to go 😦

They ARE making significant progress on our house though. Here is what it looked like at the end of May…

May30

Day #17

The framing happened fast. It took about 3 weeks. I took the picture below after they had already moved on to the mechanical work inside.

Day #46

Day #46

And speaking of inside…It’s hard to take a meaningful picture because unless you’re familiar with the floor plan, it really just looks like a lot of 2×4’s everywhere. But this picture actually includes quite a few of the rooms in the house.

A view of the inside

At this point, they are working on “boring” but important things like installing duct work, plumbing and electrical. We’ve already made super important decisions like which light switches control which outlets and where the recessed lights in the kitchen will go (“Here-ish,” I said, drawing an imaginary line in the kitchen with my finger. The builder did not hesitate to tease me about my precision 🙂 )

We were more precise with our decisions on the kitchen cabinets which have also been finalized and ordered!

Kitchen

Kitchen

In the next month, they should be finishing up the mechanical work, putting up drywall, and installing the kitchen. We will really be getting close by then. Here’s hoping July moves along at a reasonable pace!